COMMUNITY NOTICE
Upcoming operations

Rock Blasting at the Valeo Project

What Vistancia neighbors should know about upcoming drilling and blasting operations.

What to expect

Project at a glance

Location
Vistancia, west of N Vistancia Blvd and south of W Lone Mountain Rd
Schedule
Anticipated late October 2026 through late January 2027
Duration
Approximately 3 months of drilling and blasting
Frequency
2–3 blasts per week

Project area

Where blasting will take place

The Valeo Project site is located in Vistancia, west of N Vistancia Blvd and south of W Lone Mountain Rd. The map below shows the project limits.

Aerial map showing the Valeo Project limits near N Vistancia Blvd and W Lone Mountain Rd
Valeo Project limits · Drill and blast area

Licensed, permitted and designed for safety

FNF Construction is a licensed blasting contractor and will hold an active permit for blasting operations on this project. Every blast is individually designed to stay within industry standards for ground vibration, so that no damage occurs to nearby homes and structures.

Brief traffic holds on W Lone Mountain Rd

Traffic along Lone Mountain Rd will be stopped 1 minute before each scheduled blast and released once the Blasting Supervisor gives the “All Clear.” Please follow the directions of flaggers and posted signage.

For homes within 500–1,000 ft of the blast zone

What to expect when a blast occurs

Each blast lasts only a few seconds. What you notice will vary with your distance and your home’s construction.

01

A brief vibration underfoot

You may feel a short rumble through the floor, similar to a heavy truck passing by.

02

A dull thump or boom

A muffled sound may carry through the air a moment after the ground movement.

03

Rattling windows or loose items

Windows, doors and objects on shelves may briefly rattle. This is normal and not harmful.

04

What feels like two pulses

Your home may respond first to the ground, then to the air pressure, a split second apart.

Is my home safe?

Yes. Blasting can be felt at vibration levels far below those that could cause cracking. Every Valeo blast is designed to stay within industry safe-blasting standards, and seismographs are placed at the nearest structures to confirm vibration levels after each blast.

A helpful step before blasting begins

Walk through your home and take photos of any existing cracks in drywall, stucco, tile or concrete. Many homes have small cracks from normal settling and temperature changes that often go unnoticed until blasting draws attention to them.

Learn more

Facts About Rock Blasting

Read the guide from Arizona Monitoring Services.

arizonamonitoringservices.com

Questions about blasting?

Contact us

Reach out with any questions or concerns about the blasting operations at the Valeo Project.